Minturn North Construction Updates
Posted on: May 1, 2024 - 11:26am
The Minturn North team has created a website to provide project information and updates at:
https://www.minturnnorth.com/construction-updates. This page will include information regarding any road closures and utility shutoffs.
THIS HANDOUT should help answer many Frequently Asked Questions.
Below is a link to the Minturn North Construction Plan Set.
2024 Tentative Construction Schedule as follows with 4th St closed during this time (schedule subject to change):
Mobilization: 5/20 - 5/31
Earthwork (Cut & Fill): 5/27 - 8/5
2024 Tentative Construction Schedule as follows with 4th St closed during this time (schedule subject to change):
Mobilization: 5/20 - 5/31
Earthwork (Cut & Fill): 5/27 - 8/5
Water Main Installation: 6/3 - 8/19
Sewer Main Installation: 6/1 - 8/2
Dry Utility Installation: 7/15 - 9/15
Curb, Gutter and Paving: 8/15 - 9/23
Final Grading, Clean Up & De-Mob: 9/23 - 11/15
Sewer Main Installation: 6/1 - 8/2
Dry Utility Installation: 7/15 - 9/15
Curb, Gutter and Paving: 8/15 - 9/23
Final Grading, Clean Up & De-Mob: 9/23 - 11/15
- Construction Days/Hours are 7:00 AM to 6:00 PM Monday through Saturday.
- 48 Hours Written Notice to be provided to affected users in advance of any waterline shutdown.
- Maximum waterline shutdown length to be 6 hours.
- An electronic message board located at the Taylor St and Minturn Rd intersection will provide notices of utility outage dates/times.
- A project construction sign with safety and emergency contact information will be located at the Taylor St and Minturn Rd intersection.